AQW 49625/22-27 Written question to the Minister of Education

To ask the Minister of Education for an update on the completion of Crawfordsburn Primary School's new build.

Asked by Connie Egan MLA on 25 June 2026

  • Answered
  • Written
Tabled
25 June 2026
Answer due by
10 July 2026
Answered
3 July 20268 days after tabling
Department
Department of Education
Priority question
No

Answer

Construction work for the new school building commenced on site in September 2025 and the building is scheduled to be handed over to the school in Spring 2027.

Following completion of the new building the existing school will be demolished and the external site works will be completed.

The overall project is scheduled for completion in Summer 2027.