AQW 29263/22-27 Written question to the Minister of Education
To ask the Minister of Education to detail an update on the timescale for a new building for Crawfordsburn Primary School.
Asked by Connie Egan MLA on 25 June 2025
- Answered
- Written
- Tabled
- 25 June 2025
- Answer due by
- 10 July 2025
- Answered
- 30 June 20255 days after tabling
- Department
- Department of Education
- Priority question
- No
Answer
The contract for the construction of the new school building for Crawfordsburn Primary School was awarded to Bell Contracts Ltd on 14 May 2025.
Construction is due to commence on site in July 2025 with completion programmed for November 2026.