AQW 17965/22-27 Written question to the Minister for Communities

To ask the Minister for Communities to detail the reasons for the delay of Marine Gardens Public Realm Project, Bangor, until January 2025.

Asked by Connie Egan MLA on 11 November 2024

  • Answered
  • Written
  • After due date
  • Priority
Tabled
11 November 2024
Answer due by
14 November 2024
Answered
27 November 202416 days after tabling
Department
Department for Communities
Priority question
Yes

Answer

Significant progress has been made over recent weeks and months, and the final planning approval has been granted by Ards and North Down Borough Council’s Planning Committee, at its meeting on 5 November 2024.

Completion of the necessary legal agreements is anticipated in the coming weeks which will pave the way for construction of Phase 1 to commence in January 2025. This has been delayed to minimise the impact to trade in the city centre during the busy holiday period.