AQW 15857/22-27 Written question to the Minister for Infrastructure
To ask the Minister for Infrastructure for his assessment of the impact that the closure of the Great Victoria Street station in May 2024 has had on the number of rail journeys on the Belfast to Bangor line.
Asked by Connie Egan MLA on 27 September 2024
- Answered
- Written
- After due date
- Tabled
- 27 September 2024
- Answer due by
- 14 October 2024
- Answered
- 15 October 202418 days after tabling
- Department
- Department for Infrastructure
- Priority question
- No
Answer
Passenger journeys on the Bangor Corridor between May and September 2024 were down 14% on the same period in 2023.