AQO 163/22-27 Oral question to the Minister for Communities
To ask the Minister for Communities for an update on the regeneration of Queen’s Parade, Bangor.
Asked by Connie Egan MLA on 29 February 2024
- Answered
- Oral
- Answered in the Chamber
- Tabled
- 29 February 2024
- Answer due by
- 12 March 2024
- Answered
- 12 March 202412 days after tabling
- Department
- Department for Communities
- Priority question
- No
Answer
Answered in the Assembly Chamber on 12 March 2024. Extract from the Official Report (Hansard), including any supplementary questions:
Mr Lyons
My officials have been working closely with Ards and North Down Borough Council and the developer, Bangor Marine, to bring forward plans for the development of the site by way of a development agreement. I take this opportunity to pay tribute to officials from the Department for Communities who have worked very hard on this over many years. The Bangor Marine team is working through the pre-commencement planning conditions. In tandem with that, discussions continue with the Crown Estate about securing the necessary approvals for elements of the project that will be located on Crown Estate land. Bangor Marine has started to clear trees and shrubbery from the Marine Gardens part of the site, in advance of the nesting season, to accommodate the commencement of the construction of the public realm works, which are programmed to begin later this year. That will provide an economic boost to the wider Ards and North Down economy through increased tourism, city-centre living and increased employment opportunities.
Ms Egan
Thank you, Minister. The Queen's Parade site in Bangor has been derelict since before I was born. People in Bangor are very keen to see the regeneration happen. Unfortunately, the project has been plagued by delays. On your Department's website, it is stated that works were expected to start in summer 2023. When can we expect building to take place? Can you give the people of Bangor hope that you will prioritise the project?
Mr Lyons
I always hope that I can give the people of Bangor hope. Hopefully, I will do that in many ways in the remainder of my time in office. I completely understand the frustration over the site. As the Member indicated, this has been going on for many decades. I know that people in the area have wanted to see the site progress for a long time. She will be aware of the negotiations that I mentioned with the Crown Estate. Those negotiations have been somewhat protracted. They have gone on a lot longer than any of us would have liked them to and, as a result, could push back the planned start date of this summer. The Member will, however, be aware of the works that have taken place so far, and I can give her an assurance that the issue will be pushed forward by my Department so that the regeneration happens as quickly as possible. I am delighted that I will very soon be visiting the site to see for myself the work that is going to be done. It was on my first or second day in office that Mr Dunne extended an invitation to me to visit it, so I look forward to seeing the potential that is there. It could be an absolute game changer, bringing significant economic and social benefits for the people of Bangor and, indeed, more widely.
Mr Chambers
I welcome the Minister's comments. Have any time limits been incorporated into the contract with the developer to ensure that the project's various stages are completed on time?
Mr Lyons
I am not aware of any hard and fast dates having been included to ensure that the work is completed. The target date is spring 2027, and I certainly hope that the work can be progressed and finished. As I said in my answer to Ms Egan, I will do everything that I can, where my Department has responsibility, to make sure that the project is moved on as quickly as possible. I understand the benefits that it can bring, and I want people to enjoy those benefits as soon as possible.
Mr McCrossan
Will the Minister provide an update on the regeneration of Strabane town centre and what progress has been made on the public realm scheme?
Mr Lyons
Yes. This is another area that has been some time in the making. The Strabane public realm project is at the business case stage and is now scheduled for casework committee consideration within my Department. There have been a number of iterations of the business case, and my officials have been working closely with Londonderry and Strabane District Council in getting the business case finalised for casework consideration over the past months. The project is of a scale that will require my approval as well as the Department of Finance's approval. In consideration of the project, I will want to consider the budget requirements alongside other capital funding priorities within my Department.